Regulations 10 and 14 connect MHI risk information with municipal land-use decisions and public participation. The duty holder and local government have distinct responsibilities under the 2022 Regulations.
South Africa’s Major Hazard Installation Regulations give local government specific land-use and emergency-planning duties. Regulation 14 restricts approval of a new establishment, expansion, or certain nearby developments where the separation distance would pose an unacceptable risk under the regulation 10 risk assessment. The duty holder supplies risk information when required; the Regulations do not create a universal neighbour-consultation sequence or let an operator decide whether a municipal development application should be approved.
Updated, 3 November 2026: Corrected the former article’s misattribution of public-information duties to regulations 6, 8, and 17, removed an unsupported universal 10⁻⁶ “effect zone,” and separated local-government duties from duty-holder responsibilities.
What the Regulations assign to local government
Under regulation 14, local government must not permit a new establishment or expansion at a separation distance that poses an unacceptable risk in terms of the regulation 10 assessment. It must permit new development only where the separation distance will not pose an unacceptable risk, and prohibit adjacent property development that would result in that development being declared an establishment.
The local government also gives consent for the on-site emergency plan and participates in the annual emergency exercise. It is responsible for preparing the off-site emergency plan, consulting the duty holder and interested or affected persons, and reviewing that plan when the area’s hazard profile changes significantly.
The MHI Regulations operate alongside other planning and building laws. A municipal decision must be considered under the applicable planning framework and site facts; this article is not a zoning opinion for a specific application.
What the duty holder must provide
Regulation 10 requires the risk assessment to include information about neighbours and other establishments within the impact zone, including sites likely to be affected and their distances from the establishment, known future development that may increase risk or consequences, and other establishments and their distances.
When the local government requests information needed to prepare its off-site emergency plan in writing and sets a time limit, regulation 14(7) requires the duty holder to furnish the necessary information within that period. The duty holder should record the request, supplied documents, version, date, and delivery evidence.
Regulation 10 also sets public-information and representation requirements in specific circumstances: erection of an establishment, an updated risk assessment, or conversion of an existing installation. The required advertisement and community notices include prescribed information; affected or interested parties may make written representations within 60 days after the advertisement. Check the exact trigger and prescribed content in regulation 10(4)–(5) rather than assuming a generic annual community mailing is required.
Keep the site-to-municipality interface current
Maintain a controlled information set that can support the applicable assessment, land-use review, and emergency plan. Depending on the actual site, this may include:
- current establishment address, layout, inventory, and process description;
- assessment information about potential impact and nearby establishments;
- known land-use or development information provided by the relevant authority;
- current duty-holder and emergency contacts;
- the local-government written request and the date-limited response;
- consultation, notices, representations, and submission records required by regulation 10.
Check that the risk assessment and emergency documents use consistent establishment boundaries, names, hazards, contacts, and revisions. Do not present a single risk contour or a “worst case” boundary as the legal impact zone for every site; use the actual assessment and applicable Annexure A and SANS 1461 requirements.
Plan warning and emergency coordination separately
The duty holder’s on-site emergency plan must state how employees, visitors, and neighbours will be warned, be approved by local government, remain readily available, and be exercised in practice at least annually. The duty holder must take the necessary steps to arrange local-government participation and give early warning to affected or interested parties when a major incident is likely to go beyond the establishment boundary.
The local government is responsible for the off-site emergency plan. The duty holder supplies requested information and coordinates the boundary between the on-site plan and off-site response; it does not take over the authority’s statutory responsibility.
A practical planning check
- Confirm the establishment’s category and current risk-assessment scope with an AIA.
- Ask the relevant planning and emergency-management offices what information is needed for a specific application or emergency-plan interface.
- Respond to written information requests within the stated time and keep delivery evidence.
- Verify whether a regulation 10 public-information trigger applies to the activity underway.
- Keep local-government decisions, conditions, approvals, representations, and emergency-plan exercise actions with the relevant document version.
- Obtain planning or legal advice for a live zoning application, unacceptable-risk question, or disagreement with an authority.
This guide explains the MHI Regulations only. It cannot determine a proposed development’s acceptability, a separation distance, or the legal duties that apply to a particular property without the assessment and planning records.
Frequently asked questions
Who decides whether development near an MHI presents an unacceptable risk?
Local government has the land-use duties in regulation 14 and considers the regulation 10 risk assessment. A duty holder supplies relevant information; it does not approve or refuse a municipal development application.
Does every MHI have to notify all neighbours every year?
Regulation 10 sets specified public-information duties when an establishment is erected, a risk assessment is updated, or an existing installation is converted. Regulation 15 separately requires the on-site emergency plan to explain neighbour warnings and requires early warning in the stated off-boundary incident circumstances. The Regulations do not prescribe one universal annual mailing to all neighbours.
Who prepares the off-site emergency plan?
The relevant local government is responsible for the off-site plan under regulation 14. The duty holder must provide information requested in writing and within the time limit imposed by the local government.
Does South African MHI law define a universal 10⁻⁶ contour as the neighbour boundary?
The Regulations do not establish one universal contour boundary for every site. Use the site-specific risk assessment and applicable standard and planning requirements.
Sources
- Major Hazard Installation Regulations, 2022, regulations 10, 14 and 15
- Department explanatory notes, Government Gazette 51628 (2024)